Tendersinfo keep you informed about the latest events in the national and international Procurement Industry. Procurement News provides in-depth coverage of the procurement industry, including contract awards, contract additions, new contract wins, mergers and acquisitions. Tendersinfo through its tender news section provides an update on all domestic and global tendering opportunities, invitation to bid & trade leads.

United States : PDO for Snorre Expansion Project approved

Publish Date : 11-Jul-2018

The Ministry of Petroleum and Energy has approved the plan for development and operation (PDO) for the Snorre Expansion Project. Investments of just above NOK 19 billion (2017) will increase recovery from the Snorre field by almost 200 million barrels and extend the field life beyond 2040.

Snorre Expansion Project is the largest project for improved recovery on the Norwegian continental shelf and provides valuable production and activity benefitting Equinor, partners and society. The project involves a comprehensive subsea development, upgrading of the Snorre A installation, increased gas injection and gas import for injection.

Equinor has worked closely with partners and suppliers to realise the development. I am pleased that the plan for development and operation has been approved, says Margareth vrum, Equinors executive vice president for Technology, Projects and Drilling.

The Snorre field was originally estimated to produce until 20112014. Now the field life has been extended beyond 2040, and the recovery rate increases from 46 to 51 per cent.

Scheduled to start production in 2021, the Snorre Expansion Project will be operated and maintained by the existing Snorre organisation in Stavanger. Supplies will still be handled by Fjordbase in Flor.

Equinor estimates that around 80% of the investments, which are just above NOK 19 billion, will include Norwegian companies. Based on analyses made by Agenda Kaupang approximately 23,000 man-years will be carried out in Norway in the project phase.

Subject to final regulatory approval, the partners have awarded contracts for the subsea production system to TechnipFMC, fabrication and installation of the pipeline bundle system to Subsea 7, Snorre A modifications to Aibel, drilling and well operations to Transocean and marine installations to Deep Ocean.

The project will provide jobs in many places along the Norwegian coast and operation of the Snorre field for 25 more years, says Arne Sigve Nylund, Equinors executive vice president for Development and Production Norway.